Vantage’s Project team had just successfully completed the tariff consultant, customs clearance and delivery for 6 shipments of the machinery of shoe production lines for Apex Vietnam factory in Nghe An.

- Project: Apex Vietnam factory

- Commodity: the machinery of shoe production lines

- Vantage’s scope: import tax declaration consultancy, custom clearance at Nghe An customs department, door delivery from Hai Phong port to job site at Nghe An.

- Shipment time: April 2020



 

* Shipment 1st:
- Quantity: 456 packages, total volumes 35tons (91.8CBMs), 2x40’HC
- Delivery date: March 31st, 2020
- Arrival at factory: April 1st, 2020

 

* Shipment 2nd:
- Quantity: 13 packages, total volumes 11.7tons (54.5CBMs), 1x40’HC and 1x20’DC
- Delivery date: April 1st, 2020
- Arrival at factory: April 2nd, 2020

 

* Shipment 3rd:
- Quantity: 12 packages, total volumes 11.5tons (53.4CBMs), 1x20’GP and 1x40’HC
- Delivery date: April 1st, 2020
- Arrival at factory: April 2nd, 2020

 

* Shipment 4th:
- Quantity: 12 packages, total volumes 3.7tons (26.4CBMs), 1x40’HC
- Delivery date: April 3rd, 2020
- Arrival at factory: April 4th, 2020

 

* Shipment 5th:
- Quantity: 63 packages, total volumes 14tons (50.73CBMs), 1x40’HC
- Delivery date: April 3rd, 2020
- Arrival at factory: April 4th, 2020

 

* Shipment 6th:
- Quantity: 456 packages, total volumes 35tons (91.8CMBs), 2x40’HC
- Delivery date: April 15th, 2020
- Arrival at factory: April 16th, 2020


 